Islands Campus Site Improvements Phase III - SA [See more photos]  
New 2000 seat stadium with fieldhouse and artificial turf surface.
 
Project Team
Project Manager:  Dwayne Stephens, Parsons Team
Architect/Engineer:  Thomas & Hutton
 
Budget Summary
Total Projected Budget $6,662,672
Funding Source ESPLOST III
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 201820192020
JFMAMJJASONDJFMAMJJASONDJFMA
Design 1/1/2018 10/31/2018 1/1/2018 1/18/2019
Bid / Award 10/1/2018 1/18/2019 1/20/2019 4/5/2019
Construction 1/28/2019 1/31/2020 4/8/2019 4/30/2020