Islands Campus Site Improvements Phase III - SA |
[See more photos]
|
New 2000 seat stadium with fieldhouse and artificial turf surface. |
|
Project Team |
Project Manager: Dwayne Stephens, Parsons Team |
Architect/Engineer: Thomas & Hutton |
|
Budget Summary |
Total Projected Budget |
$6,662,672 |
Funding Source |
ESPLOST III |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2018 | 2019 | 2020 | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A |
Design |
1/1/2018 |
10/31/2018 |
1/1/2018 |
1/18/2019 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Bid / Award |
10/1/2018 |
1/18/2019 |
1/20/2019 |
4/5/2019 |
| | | | | | | | |
|
|
|
| | | | | | | | | | | | |
|
|
|
| |
Construction |
1/28/2019 |
1/31/2020 |
4/8/2019 |
4/30/2020 |
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|