Woodville Tompkins HS - SA [See more photos]  
A new gymnasium will be built with the old gymnasium being converted into an auditorium.
 
Project Team
Project Manager:  Dwayne Stephens, Parsons Team
Architect/Engineer:  James W Buckley and Associates, Inc
 
Remarks
Project will be phased so gym will be completed first and remodeling for auditorium in second phase
 
Budget Summary
Total Projected Budget $13,086,000
Funding Source ESPLOST III
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 20182019202020212022
ASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJF
Design 8/27/2018 7/1/2019 8/27/2018 9/27/2019
Bid / Award 7/15/2019 9/20/2019 10/1/2019 12/20/2019
Construction - I 10/25/2019 12/25/2020 1/6/2020 2/26/2021
Construction - II 1/4/2021 12/31/2021 3/1/2021 2/25/2022