Jenkins HS - NS [See more photos]  
New 1250 FTE high school to replace existing school
 
Project Team
Project Manager:  Dwayne Stephens, Parsons Team
Architect/Engineer:  Hussey, Gay, Bell & DeYoung, Inc.
General Contractor:  JE Dunn Construction Co d/b/a Rives E Worrell Co
 
Remarks
Demolition and sitework needed for the new building is being completed.
 
Budget Summary
Total Projected Budget $69,703,900
Funding Source ESPLOST III
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 20172018201920202021
AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJ
A/E Procurement 4/24/2017 8/18/2017 5/22/2017 1/12/2018
CMR Procurement 8/1/2017 11/24/2017 2/5/2018 5/31/2018
Design 8/21/2017 4/12/2019 1/15/2018 8/20/2019
Bid/Construction 1/1/2019 7/30/2021 9/2/2019 7/30/2021
Demolition & Sitework 6/17/2019 10/31/2019 6/17/2019 10/31/2019