White Bluff ES - NS [See more photos]  
New 650 FTE replacement school on existing site
 
Project Team
Project Manager:  Brett Lundy, Parsons Team
Architect/Engineer:  James W Buckley and Associates, Inc
General Contractor:  TQ Constructors, Inc.
 
Remarks
Construction of the new school is underway and will be finished for the start of the '20-'21 school year.
 
Budget Summary
Total Projected Budget $22,905,120
Funding Source ESPLOST III
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 2017201820192020
AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJ
A/E Procurement 4/24/2017 11/30/2017 5/22/2017 1/12/2018
Design/Permit/Bid 12/1/2017 10/5/2018 1/15/2018 1/9/2019
Construction 9/3/2018 4/30/2020 2/4/2019 4/30/2020
Furniture, Move-in & Occupancy 5/1/2020 7/31/2020 5/1/2020 7/31/2020