White Bluff ES - NS |
[See more photos]
|
New 650 FTE replacement school on existing site |
|
Project Team |
Project Manager: Brett Lundy, Parsons Team |
Architect/Engineer: James W Buckley and Associates, Inc |
General Contractor:  TQ Constructors, Inc. |
|
Remarks |
Construction of the new school is underway and will be finished for the start of the '20-'21 school year. |
|
Budget Summary |
Total Projected Budget |
$22,905,120 |
Funding Source |
ESPLOST III |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2017 | 2018 | 2019 | 2020 | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J |
A/E Procurement |
4/24/2017 |
11/30/2017 |
5/22/2017 |
1/12/2018 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
12/1/2017 |
10/5/2018 |
1/15/2018 |
1/9/2019 |
| | | | | | | |
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| |
Construction |
9/3/2018 |
4/30/2020 |
2/4/2019 |
4/30/2020 |
| | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
5/1/2020 |
7/31/2020 |
5/1/2020 |
7/31/2020 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
|
|
|