Hubert MS [See more photos]  
Kitchen / Cafeteria addition / modification.
 
Project Team
Project Manager:  Brett Lundy, Parsons Team
Architect/Engineer:  CDH Partners, Inc
General Contractor:  Dabbs-Williams General Contractors LLC
 
Budget Summary
Total Projected Budget $4,680,910
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 201420152016
JFMAMJJASONDJFMAMJJASONDJFMAMJJ
A/E Procurement 1/2/2015 3/31/2015 1/2/2014 7/2/2014
Design/Permit/Bid 4/1/2015 9/29/2015 7/7/2014 8/5/2015
Construction 9/30/2015 6/15/2016 9/2/2015 7/29/2016
Furniture, Move-in & Occupancy 6/16/2016 7/27/2016 7/1/2016 7/29/2016