Brock ES [See more photos]  
Project provides for the design and construction of a new Elementary School on the existing school site to accomodate 650 students.
 
Project Team
Project Manager:  Brett Lundy, Parsons Team
Architect/Engineer:  Hussey, Gay, Bell & DeYoung, Inc.
General Contractor:  Elkins Constructors, LLC
 
Remarks
School Open
 
Budget Summary
Total Projected Budget $20,512,065
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 201420152016
JFMAMJJASONDJFMAMJJASONDJFMAMJJASOND
A/E Procurement 1/2/2014 3/31/2014 1/6/2014 4/2/2014
CMR Procurement 1/2/2014 3/31/2014 2/3/2014 5/7/2014
Design/Permit/Bid 4/1/2014 1/7/2015 4/28/2014 5/1/2015
Construction 1/8/2015 6/20/2016 6/29/2015 7/29/2016
Furniture, Move-in & Occupancy 6/21/2016 8/1/2016 7/18/2016 8/3/2016
Demolition & Sitework 5/30/2016 12/2/2016