Isle of Hope K-8 [See more photos]  
Project is a new school which is being constructed in place of the existing school. The school will have a two story side for 40 classrooms, 4 science classrooms, media center, computer lab, music and art rooms; along with a gymnasium, kitchen and dining area. The building is designed to hold 800 grade K-8 students.
 
Project Team
Architect/Engineer:  James W Buckley and Associates, Inc
General Contractor:  CPPI of Georgia, LLC
 
Remarks
The new school project is complete.
 
Budget Summary
Total Projected Budget $22,731,311
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 201320142015
JFMAMJJASONDJFMAMJJASONDJFMAMJJA
A/E Procurement 1/2/2013 4/30/2013 1/2/2013 8/28/2013
CMR Procurement 1/2/2013 4/30/2013 1/2/2013 9/13/2013
Design/Permit/Bid 5/1/2013 2/6/2014 8/29/2013 4/15/2014
Construction 2/7/2014 6/18/2015 3/13/2014 7/24/2015
Furniture, Move-in & Occupancy 6/19/2015 7/30/2015 6/19/2015 8/5/2015