Hesse K-8 |
[See more photos]
|
Project is a replacement school which will be constructed next to the existing school. The school will have a gymnasium with hardwood flooring; kitchen and cafeteria; media center with a computer lab; and a two story classroom wing with 58 classrooms, 4 science classrooms, teacher workrooms and resource rooms. There are also separate classrooms for music and art. The school is designed to accommodate 1,150 grade K-8 students. |
|
Project Team |
Architect/Engineer: Cogdell & Mendrala Architects |
General Contractor:  JE Dunn Construction Co d/b/a Rives E Worrell Co |
|
Remarks |
The new school project is complete. |
|
Budget Summary |
Total Projected Budget |
$28,290,882 |
Funding Source |
ESPLOST II |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2013 | 2014 | 2015 | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D |
A/E Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
6/7/2013 |
|
|
|
|
|
|
|
|
|
| |
CMR Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
9/20/2013 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
5/1/2013 |
2/6/2014 |
6/10/2013 |
5/2/2014 |
| | | |
|
|
|
|
|
|
|
|
|
| | | | | |
|
|
|
|
|
|
|
|
|
|
|
| |
Construction |
2/7/2014 |
6/18/2015 |
4/14/2014 |
7/24/2015 |
| | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
6/19/2015 |
7/30/2015 |
6/19/2015 |
8/5/2015 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
Demolition & Sitework |
|
|
5/26/2015 |
12/31/2015 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
| |
|
|
|