| Islands Campus Site Improvements Phase III - SA |
[See more photos]
|
| New 2000 seat stadium with fieldhouse and artificial turf surface. |
| |
| Project Team |
| Project Manager: Dwayne Stephens, Parsons Team |
| Architect/Engineer: Thomas & Hutton |
| |
| Budget Summary |
| Total Projected Budget |
$6,662,672 |
| Funding Source |
ESPLOST III |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2018 | 2019 | 2020 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A |
| Design |
1/1/2018 |
10/31/2018 |
1/1/2018 |
1/18/2019 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Bid / Award |
10/1/2018 |
1/18/2019 |
1/20/2019 |
4/5/2019 |
| | | | | | | | |
|
|
|
| | | | | | | | | | | | |
|
|
|
| |
| Construction |
1/28/2019 |
1/31/2020 |
4/8/2019 |
4/30/2020 |
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
| |