New Hampstead K-8 - NS |
[See more photos]
|
Current work includes site grading, landscape, irrigation, paving, canopies, flooring, and cleanup. |
|
Project Team |
Project Manager: Lorne George, Parsons Team |
Architect/Engineer: Perkins and Will, Inc. |
|
Budget Summary |
Total Projected Budget |
$44,072,600 |
Funding Source |
ESPLOST III |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2017 | 2018 | 2019 | 2020 | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J |
A/E Procurement |
4/24/2017 |
8/18/2017 |
5/22/2017 |
5/7/2018 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
Design |
8/21/2017 |
10/31/2018 |
5/7/2018 |
6/7/2019 |
| | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Construction |
11/1/2018 |
7/31/2020 |
11/1/2018 |
7/31/2020 |
| | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
6/26/2020 |
7/31/2020 |
6/26/2020 |
7/31/2020 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| |
|
|
|