New Hampstead K-8 - NS [See more photos]  
Current work includes site grading, landscape, irrigation, paving, canopies, flooring, and cleanup.
 
Project Team
Project Manager:  Lorne George, Parsons Team
Architect/Engineer:  Perkins and Will, Inc.
 
Budget Summary
Total Projected Budget $44,072,600
Funding Source ESPLOST III
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 2017201820192020
AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJ
A/E Procurement 4/24/2017 8/18/2017 5/22/2017 5/7/2018
Design 8/21/2017 10/31/2018 5/7/2018 6/7/2019
Construction 11/1/2018 7/31/2020 11/1/2018 7/31/2020
Furniture, Move-in & Occupancy 6/26/2020 7/31/2020 6/26/2020 7/31/2020