| Woodville Tompkins HS - SA |
[See more photos]
|
| A new gymnasium will be built with the old gymnasium being converted into an auditorium. |
| |
| Project Team |
| Project Manager: Dwayne Stephens, Parsons Team |
| Architect/Engineer: James W Buckley and Associates, Inc |
| |
| Remarks |
| Project will be phased so gym will be completed first and remodeling for auditorium in second phase |
| |
| Budget Summary |
| Total Projected Budget |
$13,086,000 |
| Funding Source |
ESPLOST III |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2018 | 2019 | 2020 | 2021 | 2022 | | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F |
| Design |
8/27/2018 |
7/1/2019 |
8/27/2018 |
9/27/2019 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Bid / Award |
7/15/2019 |
9/20/2019 |
10/1/2019 |
12/20/2019 |
| | | | | | | | | | |
|
|
| | | | | | | | | | | | | | |
|
|
| |
| Construction - I |
10/25/2019 |
12/25/2020 |
1/6/2020 |
2/26/2021 |
| | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Construction - II |
1/4/2021 |
12/31/2021 |
3/1/2021 |
2/25/2022 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
| |