| Beach HS Auditorium - SA |
[See more photos]
|
| Auditorium Addition |
| |
| Project Team |
| Project Manager: Brett Lundy, Parsons Team |
| Architect/Engineer: J.W. Robinson & Associates |
| |
| Remarks |
| The new auditorium at Beach High School will include 600 seats, a raised stage, a scene shop, dressing rooms, and state of the art sound and lighting systems. |
| |
| Budget Summary |
| Total Projected Budget |
$7,200,000 |
| Funding Source |
ESPLOST III |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2017 | 2018 | 2019 | 2020 | | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A |
| A/E Procurement |
4/24/2017 |
8/18/2017 |
5/22/2017 |
2/2/2018 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
| Design |
2/5/2018 |
2/15/2019 |
2/5/2018 |
6/7/2019 |
| | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Bid/Construction |
2/18/2019 |
6/30/2020 |
6/9/2019 |
8/28/2020 |
| | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
7/1/2020 |
7/31/2020 |
8/24/2020 |
8/28/2020 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| |
|
|
| |