Jenkins HS - NS |
[See more photos]
|
New 1250 FTE high school to replace existing school |
|
Project Team |
Project Manager: Dwayne Stephens, Parsons Team |
Architect/Engineer: Hussey, Gay, Bell & DeYoung, Inc. |
General Contractor:  JE Dunn Construction Co d/b/a Rives E Worrell Co |
|
Remarks |
Demolition and sitework needed for the new building is being completed. |
|
Budget Summary |
Total Projected Budget |
$69,703,900 |
Funding Source |
ESPLOST III |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2017 | 2018 | 2019 | 2020 | 2021 | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J |
A/E Procurement |
4/24/2017 |
8/18/2017 |
5/22/2017 |
1/12/2018 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
CMR Procurement |
8/1/2017 |
11/24/2017 |
2/5/2018 |
5/31/2018 |
| | | |
|
|
|
| | | | | | | | | | |
|
|
|
| |
Design |
8/21/2017 |
4/12/2019 |
1/15/2018 |
8/20/2019 |
| | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Bid/Construction |
1/1/2019 |
7/30/2021 |
9/2/2019 |
7/30/2021 |
| | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Demolition & Sitework |
6/17/2019 |
10/31/2019 |
6/17/2019 |
10/31/2019 |
| | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
| |
|
|
|