|
|
Multi-School - NS |
[See more photos]
|
Current work includes site grading, landscaping, irrigation, paving, flooring, cleanup and demolition of old school after new school is completed. |
|
Project Team |
Project Manager: Lorne George, Parsons Team |
|
Budget Summary |
Total Projected Budget |
$117,485,000 |
Funding Source |
ESPLOST III |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2019 | 2020 | 2021 | 2022 | 2023 | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D |
A/E Procurement |
4/1/2019 |
7/26/2019 |
4/1/2019 |
9/20/2019 |
|
|
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
8/1/2019 |
9/30/2020 |
9/20/2019 |
9/30/2020 |
| | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| |
Construction - Site |
6/1/2023 |
12/29/2023 |
6/1/2023 |
12/29/2023 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
| |
Construction |
10/1/2020 |
8/1/2023 |
10/1/2020 |
8/1/2023 |
| | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|