Savannah HS - SA |
[See more photos]
|
Project scope includes a new CTAE Lab and renovation of an interior classroom space. This addition will include a new metals lab, as well as a new engineering lab. A new cosmetology lab will go into the space that previously held the engineering lab. |
|
Project Team |
Project Manager: Brett Lundy, Parsons Team |
Architect/Engineer: Cogdell & Mendrala Architects |
General Contractor:  Dabbs-Williams General Contractors LLC |
|
Budget Summary |
Total Projected Budget |
$3,483,000 |
Funding Source |
ESPLOST III |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2017 | 2018 | 2019 | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A |
A/E Procurement |
4/3/2017 |
5/3/2017 |
4/3/2017 |
5/3/2017 |
|
|
|
| |
Design |
5/4/2017 |
10/31/2017 |
5/4/2017 |
12/22/2017 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| |
Bid/Construction |
11/1/2017 |
12/21/2018 |
1/28/2018 |
4/30/2019 |
| | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
3/24/2019 |
3/31/2019 |
4/22/2019 |
4/30/2019 |
| | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | |
| |
|
|
|