| White Bluff ES - NS |
[See more photos]
|
| New 650 FTE replacement school on existing site |
| |
| Project Team |
| Project Manager: Brett Lundy, Parsons Team |
| Architect/Engineer: James W Buckley and Associates, Inc |
| General Contractor:  TQ Constructors, Inc. |
| |
| Remarks |
| Construction of the new school is underway and will be finished for the start of the '20-'21 school year. |
| |
| Budget Summary |
| Total Projected Budget |
$22,905,120 |
| Funding Source |
ESPLOST III |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2017 | 2018 | 2019 | 2020 | | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J |
| A/E Procurement |
4/24/2017 |
11/30/2017 |
5/22/2017 |
1/12/2018 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
| Design/Permit/Bid |
12/1/2017 |
10/5/2018 |
1/15/2018 |
1/9/2019 |
| | | | | | | |
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Construction |
9/3/2018 |
4/30/2020 |
2/4/2019 |
4/30/2020 |
| | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
5/1/2020 |
7/31/2020 |
5/1/2020 |
7/31/2020 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
|
|
| |