Woodville-Tompkins Tech |
[See more photos]
|
Auto Lab Addition |
|
Project Team |
Project Manager: Lorne George, Parsons Team |
Architect/Engineer: Cogdell & Mendrala Architects |
General Contractor:  Dabbs-Williams General Contractors LLC |
|
Remarks |
The CATE Lab is being occupied by students and staff. |
|
Budget Summary |
Total Projected Budget |
$6,136,884 |
Funding Source |
ESPLOST II |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2015 | 2016 | 2017 | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A |
A/E Procurement |
1/2/2015 |
3/31/2015 |
1/2/2015 |
5/6/2015 |
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
4/1/2015 |
9/29/2015 |
6/1/2015 |
5/4/2016 |
| | |
|
|
|
|
|
| | | | | |
|
|
|
|
|
|
|
|
|
|
|
| |
Construction |
9/30/2015 |
6/15/2016 |
6/7/2016 |
8/16/2017 |
| | | | | | | |
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
6/16/2016 |
7/27/2016 |
7/31/2017 |
8/16/2017 |
| | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| |
|
|
|