| Woodville-Tompkins Tech |
[See more photos]
|
| Auto Lab Addition |
| |
| Project Team |
| Project Manager: Lorne George, Parsons Team |
| Architect/Engineer: Cogdell & Mendrala Architects |
| General Contractor:  Dabbs-Williams General Contractors LLC |
| |
| Remarks |
| The CATE Lab is being occupied by students and staff. |
| |
| Budget Summary |
| Total Projected Budget |
$6,136,884 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2015 | 2016 | 2017 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A |
| A/E Procurement |
1/2/2015 |
3/31/2015 |
1/2/2015 |
5/6/2015 |
|
|
|
|
|
|
|
| |
| Design/Permit/Bid |
4/1/2015 |
9/29/2015 |
6/1/2015 |
5/4/2016 |
| | |
|
|
|
|
|
| | | | | |
|
|
|
|
|
|
|
|
|
|
|
| |
| Construction |
9/30/2015 |
6/15/2016 |
6/7/2016 |
8/16/2017 |
| | | | | | | |
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/16/2016 |
7/27/2016 |
7/31/2017 |
8/16/2017 |
| | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| |
|
|
| |