Garrison Performing Arts Center |
[See more photos]
|
Performance space addition/renovation |
|
Project Team |
Project Manager: Brett Lundy, Parsons Team |
Architect/Engineer: Greenline Architecture |
General Contractor:  Lavender & Associates |
|
Budget Summary |
Total Projected Budget |
$8,439,559 |
Funding Source |
ESPLOST II |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2014 | 2015 | 2016 | 2017 | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N |
A/E Procurement |
1/2/2014 |
3/31/2014 |
1/20/2014 |
7/18/2014 |
|
|
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
4/1/2014 |
9/30/2014 |
7/14/2014 |
4/29/2016 |
| | |
|
|
|
|
|
| | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Construction |
10/1/2014 |
6/17/2015 |
6/15/2016 |
11/3/2017 |
| | | | | | | | |
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
6/18/2015 |
7/29/2015 |
10/30/2017 |
11/3/2017 |
| | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| |
|
|
|