| Islands HS |
[See more photos]
|
| Phase two of the Islands High School additions and modifications project. Renovation of the old gymnasium will produce a brand new auditorium, lobby, and back-of-stage area. |
| |
| Project Team |
| Project Manager: Ross Cairney, Parsons Team |
| Architect/Engineer: James W Buckley and Associates, Inc |
| General Contractor:  Lavender & Associates |
| |
| Remarks |
| Building has been completed and is in use! |
| |
| Budget Summary |
| Total Projected Budget |
$10,244,650 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2013 | 2014 | 2015 | 2016 | 2017 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F |
| A/E Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
8/30/2013 |
|
|
|
|
|
|
|
|
|
|
|
| |
| Design |
5/1/2013 |
9/25/2013 |
9/2/2013 |
3/28/2014 |
| | | |
|
|
|
|
| | | | | | | | |
|
|
|
|
|
|
| |
| Bid/Construction |
9/26/2013 |
6/12/2014 |
6/24/2014 |
8/5/2015 |
| | | | | | | |
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/13/2014 |
7/25/2014 |
7/27/2015 |
8/5/2015 |
| | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| |
| Cafeteria Renovations |
6/1/2015 |
9/30/2015 |
6/1/2015 |
9/30/2015 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
| |
| Auditorium Addition |
2/1/2016 |
2/1/2017 |
2/12/2016 |
2/17/2017 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
| |