Islands HS [See more photos]  
Phase two of the Islands High School additions and modifications project. Renovation of the old gymnasium will produce a brand new auditorium, lobby, and back-of-stage area.
 
Project Team
Project Manager:  Ross Cairney, Parsons Team
Architect/Engineer:  James W Buckley and Associates, Inc
General Contractor:  Lavender & Associates
 
Remarks
Building has been completed and is in use!
 
Budget Summary
Total Projected Budget $10,244,650
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 20132014201520162017
JFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJF
A/E Procurement 1/2/2013 4/30/2013 1/2/2013 8/30/2013
Design 5/1/2013 9/25/2013 9/2/2013 3/28/2014
Bid/Construction 9/26/2013 6/12/2014 6/24/2014 8/5/2015
Furniture, Move-in & Occupancy 6/13/2014 7/25/2014 7/27/2015 8/5/2015
Cafeteria Renovations 6/1/2015 9/30/2015 6/1/2015 9/30/2015
Auditorium Addition 2/1/2016 2/1/2017 2/12/2016 2/17/2017