| Coastal MS |
[See more photos]
|
| The project is a new gymnasium addition to the school. The addition is approximately 17,500 SF in size and will include a gymnasium, boys and girls bathrooms, and locker rooms. The gym will have a hardwood floor and bleachers to seat up to 800 people. There are two sets of boys and girls locker rooms including one large enough for football. |
| |
| Project Team |
| Project Manager: Ross Cairney, Parsons Team |
| Architect/Engineer: James W Buckley and Associates, Inc |
| General Contractor:  Dabbs-Williams General Contractors LLC |
| |
| Remarks |
| Performance hall and gym are ready for use. |
| |
| Budget Summary |
| Total Projected Budget |
$3,667,282 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2013 | 2014 | 2015 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M |
| A/E Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
8/30/2013 |
|
|
|
|
|
|
|
|
|
|
|
| |
| Design |
5/1/2013 |
9/30/2013 |
9/2/2013 |
1/24/2014 |
| | | |
|
|
|
|
| | | | | | | | |
|
|
|
|
| |
| Bid/Construction |
10/1/2013 |
6/17/2014 |
1/27/2014 |
3/15/2015 |
| | | | | | | | |
|
|
|
|
|
|
|
|
| | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/18/2014 |
7/30/2014 |
3/16/2015 |
3/27/2015 |
| | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| |
|
|
| |