Spencer ES |
[See more photos]
|
Project provides for the design and construction of a new Elementary School to accommodate 650 grade K to 5 students. The school design has a classical facade with the front of the building facing Wheaton Street.
The site is located on the existing Spencer E.S. campus located at 100 Bouhan Avenue.
The building will have 37 classrooms, an art room, a music room, a computer lab, media center and a gymnasium. A stage will be located in the gymnasium |
|
Project Team |
Architect/Engineer: Cogdell & Mendrala Architects |
General Contractor:  JE Dunn Construction Co d/b/a Rives E Worrell Co |
|
Remarks |
Project complete. |
|
Budget Summary |
Total Projected Budget |
$24,370,000 |
Funding Source |
ESPLOST II |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2015 | 2016 | 2017 | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D |
A/E Procurement |
1/2/2015 |
3/31/2015 |
1/2/2015 |
3/31/2015 |
|
|
|
|
|
| |
CMR Procurement |
1/2/2015 |
3/31/2015 |
1/2/2015 |
6/17/2015 |
|
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
4/1/2015 |
1/6/2016 |
4/1/2015 |
8/5/2016 |
| | |
|
|
|
|
|
|
|
|
|
| | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Construction |
1/7/2016 |
6/20/2017 |
8/22/2016 |
11/30/2017 |
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
6/21/2017 |
8/1/2017 |
12/1/2017 |
12/29/2017 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| |
|
|
|