| Low ES |
[See more photos]
|
| Project provides for the design and construction of a new Elementary School to accomodate 950 students. |
| |
| Project Team |
| Project Manager: Ross Cairney, Parsons Team |
| Architect/Engineer: Hussey, Gay, Bell & DeYoung, Inc. |
| |
| Remarks |
| Project completed. |
| |
| Budget Summary |
| Total Projected Budget |
$30,173,414 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2015 | 2016 | 2017 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A |
| A/E Procurement |
1/2/2015 |
3/31/2015 |
1/2/2015 |
3/31/2015 |
|
|
|
|
|
| |
| CMR Procurement |
1/2/2015 |
3/31/2015 |
1/2/2015 |
11/18/2015 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Design/Permit/Bid |
4/1/2015 |
1/6/2016 |
4/1/2015 |
2/17/2016 |
| | |
|
|
|
|
|
|
|
|
|
| | | |
|
|
|
|
|
|
|
|
|
|
| |
| Construction |
1/7/2016 |
6/20/2017 |
3/28/2016 |
7/24/2017 |
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/21/2017 |
8/1/2017 |
6/21/2017 |
8/2/2017 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
| Demolition & Sitework |
|
|
6/1/2017 |
8/25/2017 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
|
|
| |