Low ES [See more photos]  
Project provides for the design and construction of a new Elementary School to accomodate 950 students.
 
Project Team
Project Manager:  Ross Cairney, Parsons Team
Architect/Engineer:  Hussey, Gay, Bell & DeYoung, Inc.
 
Remarks
Project completed.
 
Budget Summary
Total Projected Budget $30,173,414
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 201520162017
JFMAMJJASONDJFMAMJJASONDJFMAMJJA
A/E Procurement 1/2/2015 3/31/2015 1/2/2015 3/31/2015
CMR Procurement 1/2/2015 3/31/2015 1/2/2015 11/18/2015
Design/Permit/Bid 4/1/2015 1/6/2016 4/1/2015 2/17/2016
Construction 1/7/2016 6/20/2017 3/28/2016 7/24/2017
Furniture, Move-in & Occupancy 6/21/2017 8/1/2017 6/21/2017 8/2/2017
Demolition & Sitework 6/1/2017 8/25/2017