| Brock ES |
[See more photos]
|
| Project provides for the design and construction of a new Elementary School on the existing school site to accomodate 650 students. |
| |
| Project Team |
| Project Manager: Brett Lundy, Parsons Team |
| Architect/Engineer: Hussey, Gay, Bell & DeYoung, Inc. |
| General Contractor:  Elkins Constructors, LLC |
| |
| Remarks |
| School Open |
| |
| Budget Summary |
| Total Projected Budget |
$20,512,065 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2014 | 2015 | 2016 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D |
| A/E Procurement |
1/2/2014 |
3/31/2014 |
1/6/2014 |
4/2/2014 |
|
|
|
|
|
|
| |
| CMR Procurement |
1/2/2014 |
3/31/2014 |
2/3/2014 |
5/7/2014 |
|
|
| |
|
|
|
| |
| Design/Permit/Bid |
4/1/2014 |
1/7/2015 |
4/28/2014 |
5/1/2015 |
| | |
|
|
|
|
|
|
|
|
|
| | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Construction |
1/8/2015 |
6/20/2016 |
6/29/2015 |
7/29/2016 |
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/21/2016 |
8/1/2016 |
7/18/2016 |
8/3/2016 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| |
| Demolition & Sitework |
|
|
5/30/2016 |
12/2/2016 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
| |
|
|
| |