| Rice Creek School |
[See more photos]
|
| Project is a new school that will be constructed on a new site in the Rice Hope residential development located at Market Blvd. and Mulberry Avenue. When the school opens it is planned to be a Grade 3 - 8 school. The school will have a gymnasium with hardwood flooring; kitchen and cafeteria; media center with a computer lab; science labs, two art rooms; music and band room; teacher workrooms and resource rooms. The school is designed to accommodate 1,000 students, with the potential to expand to 1,200 students in the future. |
| |
| Project Team |
| Architect/Engineer: BRPH |
| General Contractor:  Gilbane Building Company |
| |
| Remarks |
| New school to be built on new site. Building is designed to accommodate a future 200 student addition.
School is scheduled to open August 2015. |
| |
| Budget Summary |
| Total Projected Budget |
$28,638,725 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2013 | 2014 | 2015 | 2016 | | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A |
| A/E Procurement |
1/2/2014 |
3/31/2014 |
6/26/2013 |
7/12/2013 |
| | | | | | |
|
|
|
|
| |
| CMR Procurement |
1/2/2014 |
3/31/2014 |
7/1/2013 |
10/10/2013 |
| | | | | | |
|
|
| |
|
|
|
| |
| Design/Permit/Bid |
4/1/2014 |
1/7/2015 |
7/15/2013 |
4/30/2014 |
| | | | | | | | | |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
| Construction |
1/8/2015 |
6/20/2016 |
5/12/2014 |
7/24/2015 |
| | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/21/2016 |
8/1/2016 |
6/19/2015 |
8/5/2015 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
|
|
| |