|
|
| |
| Howard ES |
[See more photos]
|
| Project provides for the design and construction of a new Elementary School to accommodate 750 grade k to 5 students.
The site is located at 115 Wilmington Island Road.
The school will have 46 classrooms, an art room, a music room, a computer lab, a library / media center and a gymnasium. |
| |
| Project Team |
| Architect/Engineer: Cogdell & Mendrala Architects |
| General Contractor:  Ajax Building Corporation of Georgia |
| |
| Remarks |
| Current work includes site grading, landscape, irrigation, paving, canopies, flooring, cleanup, and demolition of the old school. |
| |
| Budget Summary |
| Total Projected Budget |
$25,155,187 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2014 | 2015 | 2016 | 2017 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S |
| A/E Procurement |
1/2/2014 |
3/31/2014 |
1/6/2014 |
4/2/2014 |
|
|
|
|
|
|
| |
| CMR Procurement |
1/2/2014 |
3/31/2014 |
2/3/2014 |
5/7/2014 |
|
|
| |
|
|
|
| |
| Design/Permit/Bid |
4/1/2014 |
1/7/2015 |
4/23/2014 |
1/13/2016 |
| | |
|
|
|
|
|
|
|
|
|
| | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Construction |
1/8/2015 |
6/20/2016 |
2/1/2016 |
7/25/2017 |
| | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/21/2016 |
8/1/2016 |
6/21/2017 |
8/2/2017 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
| Demolition & Sitework |
|
|
6/1/2017 |
9/29/2017 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
|
| |
|
|
| |