|
|
| |
| Isle of Hope K-8 |
[See more photos]
|
| Project is a new school which is being constructed in place of the existing school. The school will have a two story side for 40 classrooms, 4 science classrooms, media center, computer lab, music and art rooms; along with a gymnasium, kitchen and dining area. The building is designed to hold 800 grade K-8 students. |
| |
| Project Team |
| Architect/Engineer: James W Buckley and Associates, Inc |
| General Contractor:  CPPI of Georgia, LLC |
| |
| Remarks |
| The new school project is complete. |
| |
| Budget Summary |
| Total Projected Budget |
$22,731,311 |
| Funding Source |
ESPLOST II |
|
| |
| |
| Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2013 | 2014 | 2015 | | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A |
| A/E Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
8/28/2013 |
|
|
|
|
|
|
|
|
|
|
|
| |
| CMR Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
9/13/2013 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Design/Permit/Bid |
5/1/2013 |
2/6/2014 |
8/29/2013 |
4/15/2014 |
| | | |
|
|
|
|
|
|
|
|
|
| | | | | | | |
|
|
|
|
|
|
|
|
| |
| Construction |
2/7/2014 |
6/18/2015 |
3/13/2014 |
7/24/2015 |
| | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| Furniture, Move-in & Occupancy |
6/19/2015 |
7/30/2015 |
6/19/2015 |
8/5/2015 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
|
|
| |