Heard ES [See more photos]  
A new cafeteria, media center, enclosure of current school walkways, and Administrative wing upgrades.
 
Project Team
Project Manager:  Ross Cairney, Parsons Team
Architect/Engineer:  James W Buckley and Associates, Inc
General Contractor:  ACC Construction Co., Inc.
 
Remarks
Building complete
 
Budget Summary
Total Projected Budget $9,212,987
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 2013201420152016
JFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJF
Design 1/2/2013 3/19/2013 1/2/2013 3/19/2013
Bid/Construction 3/20/2013 4/17/2014 4/19/2013 2/21/2014
Furniture, Move-in & Occupancy 4/18/2014 5/29/2014 2/24/2014 3/14/2014
Design Phase II 7/10/2013 3/28/2014 7/10/2013 4/25/2014
Bid/Construction - Phase II 3/31/2014 6/26/2015 4/28/2014 2/1/2016
Furniture, Move-in & Occupancy - Phase II 7/31/2015 9/30/2015 1/25/2016 2/1/2016