Hodge ES |
[See more photos]
|
Project provides for the design and construction of a new Elementary School to accommodate 650 grade K to 5 students. The school will be similar to Pulaski and Gadsden Elementary Schools when complete.
The site is located adjacent to DeRenne Middle School.
The building will have 36 classrooms, an art room, a music room, a computer lab, media center and a 6,000 SF gym. |
|
Project Team |
Architect/Engineer: BRPH |
General Contractor:  Elkins Constructors, LLC |
|
Remarks |
School is complete and furnished. Construction is finished.
Contractor is addressing punch list items. |
|
Budget Summary |
Total Projected Budget |
$17,500,806 |
Funding Source |
ESPLOST II |
|
|
|
Project Phase |
|
Baseline Start |
Baseline Finish |
|
Actual/ Projected Start |
Actual/ Projected Finish | 2013 | 2014 | 2015 | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J |
A/E Procurement |
1/2/2013 |
1/25/2013 |
1/2/2013 |
3/22/2013 |
|
|
|
| |
CMR Procurement |
1/2/2013 |
4/30/2013 |
1/2/2013 |
6/28/2013 |
|
|
|
|
|
|
|
|
|
| |
Design/Permit/Bid |
1/28/2013 |
9/30/2013 |
3/25/2013 |
12/27/2013 |
|
|
|
|
|
|
|
|
| | |
|
|
|
|
|
|
|
|
|
| |
Construction |
8/1/2013 |
11/19/2014 |
11/18/2013 |
12/19/2014 |
| | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | | | | | | |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Furniture, Move-in & Occupancy |
11/20/2014 |
1/1/2015 |
11/20/2014 |
1/5/2015 |
| | | | | | | | | | | | | | | | | | | | | |
|
|
| | | | | | | | | | | | | | | | | | | | | | |
|
|
| |
|
|
|