Hodge ES [See more photos]  
Project provides for the design and construction of a new Elementary School to accommodate 650 grade K to 5 students. The school will be similar to Pulaski and Gadsden Elementary Schools when complete. The site is located adjacent to DeRenne Middle School. The building will have 36 classrooms, an art room, a music room, a computer lab, media center and a 6,000 SF gym.
 
Project Team
Architect/Engineer:  BRPH
General Contractor:  Elkins Constructors, LLC
 
Remarks
School is complete and furnished. Construction is finished. Contractor is addressing punch list items.
 
Budget Summary
Total Projected Budget $17,500,806
Funding Source ESPLOST II
 
 
Project Phase Baseline Start Baseline Finish Actual/ Projected Start Actual/ Projected Finish 201320142015
JFMAMJJASONDJFMAMJJASONDJ
A/E Procurement 1/2/2013 1/25/2013 1/2/2013 3/22/2013
CMR Procurement 1/2/2013 4/30/2013 1/2/2013 6/28/2013
Design/Permit/Bid 1/28/2013 9/30/2013 3/25/2013 12/27/2013
Construction 8/1/2013 11/19/2014 11/18/2013 12/19/2014
Furniture, Move-in & Occupancy 11/20/2014 1/1/2015 11/20/2014 1/5/2015