Over 70% of the planned expenditures will be spent building new and replacement schools or additions and renovations to existing facilities. Our progress in completing this work is shown below.

SCCPSS summary of New and Replacement Schools
 Pre-Design Work Complete Pre-Design Budget: $245,000
Chart.
 Design Work Complete Design Budget: $8,433,980
Chart.
 Construction Work Complete Construction Budget: $201,415,040
Chart.
 Summary of Total Work Complete Total Budget: $210,094,020
Chart.

SCCPSS summary of School Additions
 Pre-Design Work Complete Pre-Design Budget: $64,500
Chart.
 Design Work Complete Design Budget: $1,322,500
Chart.
 Construction Work Complete Construction Budget: $29,028,422
Chart.
 Summary of Total Work Complete Total Budget: $30,415,422
Chart.