Over 70% of the planned expenditures will be spent building new and replacement schools or additions and renovations to existing facilities. Our progress in completing this work is shown below.
| SCCPSS summary of New and Replacement Schools | |
|---|---|
| Pre-Design Work Complete | Pre-Design Budget: $245,000 |
|
Chart.
|
|
| Design Work Complete | Design Budget: $8,433,980 |
|
Chart.
|
|
| Construction Work Complete | Construction Budget: $201,415,040 |
|
Chart.
|
|
| Summary of Total Work Complete | Total Budget: $210,094,020 |
|
Chart.
|
|
| SCCPSS summary of School Additions | |
|---|---|
| Pre-Design Work Complete | Pre-Design Budget: $64,500 |
|
Chart.
|
|
| Design Work Complete | Design Budget: $1,322,500 |
|
Chart.
|
|
| Construction Work Complete | Construction Budget: $29,028,422 |
|
Chart.
|
|
| Summary of Total Work Complete | Total Budget: $30,415,422 |
|
Chart.
|
|