Over 70% of the planned expenditures will be spent building new and replacement schools or additions and renovations to existing facilities. Our progress in completing this work is shown below.
| SCCPSS summary of New and Replacement Schools | |
|---|---|
| Pre-Design Work Complete | Pre-Design Budget: $724,200 |
|
Chart.
|
|
| Design Work Complete | Design Budget: $9,470,000 |
|
Chart.
|
|
| Construction Work Complete | Construction Budget: $207,998,593 |
|
Chart.
|
|
| Summary of Total Work Complete | Total Budget: $218,192,793 |
|
Chart.
|
|
| SCCPSS summary of Additions and Modifications | |
|---|---|
| Pre-Design Work Complete | Pre-Design Budget: $220,000 |
|
Chart.
|
|
| Design Work Complete | Design Budget: $2,853,993 |
|
Chart.
|
|
| Construction Work Complete | Construction Budget: $44,297,676 |
|
Chart.
|
|
| Summary of Total Work Complete | Total Budget: $47,371,669 |
|
Chart.
|
|